Brook House Primary School

The Lion Academy Trust

This single stage Design & Build project comprised the fit-out of a new shell and core building over two levels for the purpose of creating a new 420 place, two form entry primary school.

The works comprised the internal fit-out including internal walls and linings, building services and fixtures, fittings and equipment of the ground and first floors, the external amenity and play space to the east of the building and adjustments to the perimeter fencing.

Logistically challenging, the site was below three floors of occupied flats. The site also had a tight footprint, meaning we had limited storage space.

Originally, the internal walls for the school were designed to be of block construction. This method required a lot of time within the programme to deliver and put pressure on the end date. We suggested the walls be constructed in metal stud partitions, which were quicker than block construction and guaranteed delivery for the new school year. Part way through the contract, the client asked us to supply and coordinate the loose FF&E for the school. We were able to obligate and deliver this by the completion date.

“From the outset we have been very pleased with how Logan Construction have approached this project and how diligent and thoughtful they have been throughout. The success of this project is down to a combination of our design and school operating experience matched by Logan and our technical advisors’ appetite to work collaboratively with Newlon and the Department of Education to keep things on the productive track we see before us.”

Christopher Stark
Lion Academy Trust

VIEW MORE EDUCATION PROJECTS

Becket Keys CofE Secondary School

Becket Keys CofE Secondary School

Construction of a new three storey replacement teaching block, named the Welby Building, was developed via closed panel timber frame solution on the south eastern corner of the grounds at Becket Keys.

Norton Knatchbull School

Norton Knatchbull School

Logan Construction undertook the refurbishment and upgrading of Norton Knatchbull School to deliver updated and modern buildings for current and future students.

Redhill Nursery

Redhill Nursery

Provision of a new children’s day-care nursery together with site development and external works. The project was within a new build mixed use residential development.

Wrotham School Sports Hall

Wrotham School Sports Hall

New build three-court state-of-the-art sports hall with modern changing facilities and a welcoming new reception area

Westcliff High Grammar School For Boys

Westcliff High Grammar School For Boys

Refurbishment and extension to an existing technology block at Westcliff High School for Boys.