New Hybrid Theatre

Royal Brompton & Harefield NHS Foundation Trust

A much needed extension and ground breaking theatre at the Royal Brompton Hospital in London. Logan Construction were delighted to secure this important project working in conjunction with the Royal Brompton Hospital following a high profile charity fundraising appeal.

The construction works comprised the formation of a new Hybrid operating theatre suite, which combined complex imagining equipment in an environment where different surgical procedures can take place at the same time, allowing a series of procedures which would normally take weeks, or even months, to now be done on the same day.

The project included new clinical staff changing facilities and the formation of surgical offices. The works were undertaken over several levels of the hospital, both internally and externally, where teamwork with several hospital departments ensured that effective logistics and mutually beneficial plans were put in place.

Major structure alterations to permit services and new staircases were included along with an extensive renewal of M&E services, whilst ensuring continuity of the existing ‘live’ theatre operations and critical care units which were adjacent to the construction works.

The works included groundworks, piling and drainage alterations, construction of a new steel framed building and full fit-out and provision of specialist equipment facilities.

KEY POINTS:

  • Hybrid Operating Theatre
  • Complex Imaging Equipment
  • Works carried out in ‘live’ hospital environment

LOCATION:
London

VALUE:
£2,900,000

PRINCIPAL CONSULTANTS:
WT Partnership, Ansell & Bailey, WSP Group, Wallace Whittle

PROJECT DURATION:
56 weeks

“All the works were very clearly explained, communicated and coordinated to ensure they were carried out safely, to time and that we could carry on functioning as a seven day diagnostic lab. I’ve worked with several site and contract managers and wanted to let you know that Logan Construction rate very high on my service quality list.”

Susan Benson, Microbiology Service Manager
Royal Brompton Hospital

“Thanks for showing me around the Hybrid Lab today; I was extremely impressed with the layout, workmanship and finish and am delighted we are moving to the commissioning phase. I am particularly grateful to you for managing the theatre disruption so effectively and to all members of staff adversely affected by the noise and dust.”

Professor TW Evans, Medical Director
Royal Brompton & Harefield NHS Foundation Trust

VIEW MORE SPECIALIST HEALTHCARE PROJECTS

Main Theatres Refurbishment Project

Main Theatres Refurbishment Project

Logan Construction were delighted to secure this challenging hospital theatre refurbishment project, working in partnership the Surrey and Sussex Trust.

Endoscopy Suite Refurbishment

Endoscopy Suite Refurbishment

A full refurbishment of Hammersmith Hospital Endoscopy Suite with minimum impact on the running of the hospital and the patients.

Lewisham MRI Scanner Works

Lewisham MRI Scanner Works

The MRI refurbishment project started with ten weeks of enabling works, which required us to form new facilities and undertake a phased decant programme to free up the required areas of the building.

New Linac Suite

New Linac Suite

Refurbishment and upgrade of the LINAC2 suite at the Royal Free to provide a new and modern environment which facilitated the installation of a new linear accelerator by the specialist Varian.

Interventional Radiology Unit

Interventional Radiology Unit

Comprising two distinct phases, this project comprised the modernisation of Basildon Hospital’s existing Radiology department