Queen Mary University London

Fogg Building and John Vane Science Centre

FOGG BUILDING

Upgrading of laboratory facilities across six floors of the Fogg Building on the QMUL Mile End Campus. Works included the refurbishment and remodelling of the existing floors into teaching laboratory and offices; including student reception/waiting area, toilets and staff kitchen area.

The works were carried out whilst the building was still in use. To safeguard the ongoing research and teaching facilities, we understood our responsibility to provide a logistics plan and phased programme that was targeted to minimise any potential disruption.

‘Live’ work segregated from the in-use facilities and, when necessary, students were decanted into suitable research and learning areas. This ensured their safety, whilst continuing to provide them with a tranquil setting in which to learn.

 

JOHN VANE SCIENCE CENTRE

This scheme was for the refurbishment of two under-used areas, redeveloped into one, to create a new imaging suite used to undertake cancer research.

The project started with the creation of a secure space, introducing new security doors and access system. We also had to install two partitions in the existing doorways, sealed to make them dust proof, as the adjacent room was an occupied laboratory with a scanner that required clean facilities at all times.

This was a logistically challenging project as it required working in a ‘live’ building that was often undertaking experiments during the day. We worked closely with the team at QMUL to understand their working patterns and were able to minimise noisy works when key experiments and scanning were taking place.

During 2010 Logan Construction had previously completed a £3.3m reconfiguration and refurbishment project at the John Vane Science Centre to form new laboratories, cell culture rooms, hot labs and associated write-up areas, together with offices, meeting rooms and additional seminar rooms.

KEY POINTS:

Our position as Framework Contractor for this authority has resulted in over £18m worth of work delivered within approximately refurbishment of 120 projects in the past six years.

LOCATION:
London

VALUE:

Fogg Building
£3.7M

John Vane Science Centre
£210,000

PRINCIPAL CONSULTANTS:
Troup Bywaters & Anders, Burnley Wilson Fish

PROJECT DURATION:

Fogg Building
36 weeks

John Vane Science Centre
14 weeks

“I would like to use this opportunity to thank the team for a good job done in spite of the numerous challenges experienced throughout this phase. We have together as a team achieved a great milestone against the odds.”

Emmanuel Nibo
QMUL Project Manager

VIEW MORE RESEARCH & DEVELOPMENT PROJECTS

London Zoo

London Zoo

Essential refurbishment of Nuffield Laboratories for ZSL London Zoo.

H1 Facilities

H1 Facilities

Full refurbishment of the H1 facilities located within ICL’s Hammersmith Campus.

Laindon Police Station

Laindon Police Station

This Design & Build project was for the refurbishment of the existing police station to form a new chemical enhancement laboratory for Laindon Police Station and Essex Police.

Cell Therapy Laboratories

Cell Therapy Laboratories

The Cellular Therapeutics unit is a highly specialist facility that was in urgent need of increased capacity.

University College London

University College London

Consistently placed within the global top 20 Universities, UCL is a world-leader in both research and education and Logan Construction have been working with this University since 2013 covering 19 projects to date.